Project description:
The new main entrance will
be constructed at Main Street to serve the McMaster Campus, Hamilton
Health Sciences, and provide access to the Westdale Community,
East of the Hospital. This entrance will be aligned with Emerson
Street and run between Hamilton Health Sciences and the existing
T13 Building up to Gilmour Hall.
Cost: $5 million
Engineers: Marshall Macklin and Monaghan Consulting Engineers
Contractor: King Paving
Timeline: April 4 - August 12, 2005
|
 |