Project description:

The new main entrance will be constructed at Main Street to serve the McMaster Campus, Hamilton Health Sciences, and provide access to the Westdale Community, East of the Hospital. This entrance will be aligned with Emerson Street and run between Hamilton Health Sciences and the existing T13 Building up to Gilmour Hall.

Cost:
$5 million

Engineers: Marshall Macklin and Monaghan Consulting Engineers

Contractor
: King Paving

Timeline
: April 4 - August 12, 2005